5 Year Plan - Water System

5 Year Plan - Water System
 
During the budget process, Council approves a five year plan for the reconstruction and replacement of roads, sewers and water infrastructure.  The plan is reviewed and updated annually by Council.
Road work is co-ordinated with the need to replace water and sanitary sewers to ensure that new roads are not dug up to carry out underground work.
Five year plans allow Council to forecast future expenditures and provide guidance to property owners as to the scheduling of future work.

2013 Projects

Eastwood Subdivision Reconstruction Phase 2 - Centennial Road
New water mains - Smith StFront St (from River Rd to West end), River Rd (from Front St to Valley St), Spring St (from Valley St to River Rd), Lower Spring St, Frances St (South end to Post Office), Edith Cavell Blvd (from former pump house to connect to Stanley Park)

2014 Proposed Projects
Eastwood Subdivision Reconstruction Phase 3 - Coulter Ave, Bodkin St, Lawton St, Peter St, Nora Pl, Lois Ave, Tracy St, Elm Ln

2015 Proposed Projects
New water mains - Erie St, Stanley St (extension from Elizabeth St to Catherine St), Belmont Rd (Kettle Creek Crossing), Borden Ave (from Belmont Rd to Louise St)
 
2016 Proposed Projects
New water mains - Hetty St (from Colborne St to Colonel Bostwick St)
Proper servicing - William St, Edith Cavell Blvd
 
2017 Proposed Projects
New water mains - Ryan St, Nathan St, Vineden Dr
Belmont water meter replacements